| April 2011 to ???: Two-Story, 1,120 ft2
Addition
Architect
Jim Foster
405 Lagunaria Lane
Alameda, CA 94502
510.541.6359
|
Engineer
Vincent Wu
Baseline Engineering
1504 Park Street #8
Alameda, CA 94501
510.865.4623
BaselineAlameda.com |
General Contractor
Mike Madigan
Madigan Fine Building
1721 A 8th Street
Berkeley, CA 94710
415.609.6110 |
Foundation Subcontractor
Alfredo's Concrete Pumping
13425 Dolittle Drive
San Leandro, CA 94577
510.913.7517 |
Plumbing Subcontractor
Pelican Plumbers
PO Box 3724
Oakland, CA 94609
510.812.1996
PelicanPlumbers.com |
Nicholas Roofing
1816 San Pablo Ave.
Berkeley, CA 94702
510.848.4433
NicholasRoofing.com |
 |
| The rear of the house prior to the start of construction.
The addition will extend 5 feet beyond the existing deck, or 20 feet
from the house and be 32 feet wide. It will have two levels,
with a 10 ft x 16 ft inset at the upper level for a deck. |
 |
| April 3rd. After driving up from Santa Cruz in the
morning, I demolished the deck, organized our "stuff" in the
crawl space, then mowed the lawn. It was a long but satisfying
day. |
 |
| April 15th. Foundation work. Alfredo and his crew
from "Alfredo's Concrete Pumping" in San Leandro did great work.
Specifically, they hauled away the deck debris, broke up and hauled
away the old concrete slab and footings below the deck, excavated (by
hand) for the new footings and slab, placed rebar, built forms, and
placed/finished the concrete. The only things they didn't do
are: hauling the dirt away, setting anchor bolts (Mike and I did
this), laying out the PEX for radiant floor heating (Mike and I did
this), installing drainage pipes under and around the slab (Mike did
this). |
 |
| April 15th. The new foundation will be "pinned" beneath
the existing foundation, visible in this photo in a slightly
precarious state. The reason our house isn't falling down is
that Mike installed shoring (not visible) in the crawl space to take
load off of the footing. |
 |
| April 15th. General Contractor Mike Madigan and a big
pile of dirt that was excavated by shovel and wheelbarrow. |
 |
| April 27th. Final cleanup in the footings prior to
placing the concrete at the walls. |
 |
|
 |
| April 27th. Views of the wall formwork and
plumbing. |
 |
| April 27th. The walls and footings have quite a bit of #4
rebar. |
 |
| April 27th. The concrete truck is about to arrive. |
 |
| April 27th. Our concrete subcontractor surprised us by
stripping the forms the same day as the pour and finishing the inside
of the walls. |
 |
| April 27th. Outside of south wall. |
 |
| April 27th. Inside of south wall. |
 |
| April 27th. West wall. |
 |
| April 27th. North wall. Notice how massive the
footing is. |
 |
| April 27th. Drainage pipes beneath and at the perimeter
of the slab will ensure the slab stays dry by providing a place for
water to go, if it gets under the slab somehow. |
 |
| April 27th. A drainage pipe passing through the south
wall. |
 |
| April 29th. Pex loop 1. PEX stands for cross linked
polyethylene. It is plastic tubing that is cast in the slab
which will be filled with hot water to heat the lower level. |
 |
| April 29th. Pex loop 2. |
 |
|
 |
April 29th. Small and medium anchor bolts
(left photo) and
small and large anchor bolts (right photo). The number of anchor
bolts in the addition is staggering.
52: Number of Small Anchor Bolts
8: Number of Medium Anchor Bolts
2: Number of Large Anchor Bolts |
 |
| April 29th. Small and medium concrete anchors with tape
measure for reference. |
 |
| May 4th. Placing slab concrete. The first concrete
pour took 2 trucks while the second pour took 3 trucks. Each
truck holds 9 cubic yards of concrete and costs $1200. |
 |
| May 4th. Broadcasting color into the top of the slab
concrete. The color is cream beige by Brickform (click
here for a data sheet). We wanted to have the
color premixed in the concrete but that option was too expensive. |
 |
| May 4th. Steel trowel finishing the concrete. |
 |
| May 4th. Lunch for the concrete crew, courtesy of Em. |
 |
| May 4th. Curing the slab with a sprinkler. |
 |
| May 11th. Four days worth of framing. |
 |
| May 11th. PJ next to one of the anchors and hold-downs. |
 |
| May 11th. One of the 52 5/8" diameter sill anchors and
one of the two 1" diameter anchors and associated hold-down. |
 |
| May 11th. PJ on the dirt pile, which will cost us $2000
to be hauled away. |
 |
| May 11th. After taking the picture of PJ on the dirt, he
wanted to get in on the action, and snapped this one of me. |
 |
|
 |
|
May 18th. Since we are
adding two full bathrooms, a new washer/dryer hookup, and a wet bar we
had to upgrade our water service by installing a larger diameter
copper pipe from the street. The plumbers did a nice job of digging
around our plants but due to a combination of rain and our extra
sticky mud, made a big mess. I expected them to move the mulch aside,
peel back the filter fabric, dig the trench, replace the pipe, put the
dirt back, put the fabric back, then put the mulch back. This didn't
happen and the photo at the right shows how it looks after I spent a
Sunday morning making it right. |
 |
|
May 23rd. Framing
continues, despite an unusually wet spring. |
 |
| May 23rd. The entire west wall of the house
was re-framed. To keep our living area clean, Mike built a plastic
wall about 3 feet inside of the exterior wall. |
 |
| May 23rd. Here is the aforementioned
plastic wall viewed from the inside, with the access zipper open. |
 |
|
 |
| May 23rd. On the left is a
photo between the plastic wall and the exterior wall (which will
become an interior wall). On the right is a photo of PJ with the
plastic wall zipper. |
 |
| May 31st. Framing continues despite the wet
weather. Here the 4x12 ridge beams have been installed. Normally I
take photos from the top of the dirt pile but since it rained I didn't
want to get muddy. |
 |
| June 6th. Rafters! |
 |
|
 |
|
June 6th. Left Photo: The final exterior
wall, at the stairwell, is up. Note that 4x4's are used instead of
2x4's. Right Photo: North bedroom wall with sill anchors and 5/8"
diameter hold-downs. |
.JPG) |
|
June 13th. A new access
point into the attic. |
.JPG) |
| June 13th. Scrap plywood laid down in the
attic (so I don't fall through, again). |
.JPG) |
| June 13th. Framing where the addition ties
into the west wall and roof of the existing house. |
.JPG) |
| June 13th. Bracing the new roof onto the
existing roof. |
.JPG) |
| June 13th. New roof, meet old roof. |
.JPG) |
| June 13th. The top of our new roof is flat
(actually, it slopes 1/4" per 12") to minimize the
loss of views for our neighbours. |
 |
| June 14th. Redwood fascia
boards are all installed, the plywood on the roof is next. |
 |
| June 14th. The redwood fascia is offset
from the walls to allow for ventilation. |
 |
| June 14th. Mike does super high quality
work. The fascia is: redwood, back primed, and all joints are glued
and biscuited. |
 |
| June 14th. Our local refuse company picks
up unlimited green waste twice a month. Luckily for us, green waste
includes raw wood (no paint, no pressure treated wood, no plywood,
etc). Here a eight cans of scrap that I didn't have to take to the
dump. |
 |
| June 15th. Our existing water heater is
moving from the garage to under the house. We are also getting a
second water heater for the radiant floor heating system. After we
pour a concrete slab, both will go here, in the "coffin" I had to dig
to provide more vertical clearance. The hole is 8 feet long, 3.5 feet
wide, and varies in height from 0.5 feet to 1.5 feet. |
 |
| June 17th. To save money, I'm using
Mike's truck for dump runs. Here is load number 6
(1220 pounds or 0.61
tons, $126/ton) which cost $76.86 to drop
off at the Berkeley Transfer Station. Due to the lumber rack,
the little truck holds a massive amount of material. Note that
the six dump runs I've done don't include the following: deck disposal
(by Alfredo), old concrete slab/footing disposal (by Alfredo), and
dirt disposal (not done yet). |
 |
| June 17th. Plywood on the south side of the
roof. |
 |
| June 17th. Plywood on the north side of the
roof. |
 |
| June 20th. Stairs from the existing house
into the upper level of the addition. |
.JPG) |
| June 20th. Stairs from the lower level of
the addition into the existing house. |
.
 |
| June 23rd. A protective layer of cement
board has been added over the foam which insulates our radiant slab. |
 |
| June 24th. Mike and Tim put in all 10
windows today. The windows are Integrity by Marvin which are wood
frames with an exterior cladding of fibreglass. |
 |
| June 24th. New windows on the north wall. |
 |
| June 24th. New windows on the south wall. |
 |
| June 24th. The last thing Mike and Tim did
today was to use this impressive ramp, along with winches, to move the
three-panel slider up to the second floor. |
 |
| June 25th. The building code requires that
we have at 30 inches of clear space in front of the water heaters, so
I had to expand my coffin today from 3'-6" wide to 5'-6" wide. I also
dug a trench for a perforated drain pipe, so if any water does get in
the coffin, it can escape. |
 |
| June 25th. Taking a break after lining the
coffin with filter fabric and placing drain stone. |
 |
| June 25th. Here you can see the coffin
drain pipe as it passes under the foundation to the exterior of the
house. |
 |
| June 27th. Mike and Tim wrapped the house
for us today, and put on tarps in anticipation of the rain tomorrow.
Bad luck building during the wettest June since they started recording
data in the 1850's. |
 |
| June 27th. Since the precast slab has PEX
for heating the lower level, we decided to heat the upper level the
same way. Aluminium plates will hold the PEX tight to the plywood and
help with heat transfer. Insulation between the studs will keep the
heat from going down. |
 |
| June 29th. Our master bathroom will feature
a 55-inch wide dual sink vanity from IKEA (Godmorgon wall mounted
cabinet and Odensvik sink). Here you can see Mike's instructions for
the plumbers. Since the IKEA website was fairly useless, he had to
drive to Emeryville and take measurements to determine the key
parameters. |
 |
| June 29th. Here's the closet in the lower
level that will be the new home of our stacked washer/dryer. This
will free up space in the garage for a future project of mine. |
 |
| June 29th. Walls for the water heater
slab. After allowing them to set up overnight, they will strip the
forms and pour the slab tomorrow. According to Tim, the walls took 30
60-pound sacks of concrete mix. |
 |
| June 30th. Slab for the water heaters,
which should go in tomorrow. |
 |
| June 30th. PJ and the beautiful 3-panel
sliding French door at the lower level. As with the windows, the door
is Integrity by Marvin (wood frame with fibreglass exterior cladding). |
 |
| June 30th. A view of the inside of the
lower level sliding French doors. Both Em and I would have preferred
swinging rather than sliding doors, but screen options are much better
with the latter, and Em is a mosquito magnet, so we went with sliders. |
 |
| July 1st. Torch-down roof at the deck. |
 |
| |
 |
| July 1st. Two stacked photos showing the plumbing on the north
wall at the lower bathroom. |
 |
| July 1st. Plumbing for the wet bar at the lower level. |
 |
| July 1st. Exterior trim is going up. The material is
finger-jointed New Zealand radiata pine that is pressure treated to
achieve 100% sapwood penetration with a wood preservative that is
effective against both fungi (rot) and insects (termites). For more
information see BodyGuardWood.com or click
here for a data sheet. In addition to using this great product,
Mike is also using two biscuits per joint. |
 |
|
 |
| July 2nd. After a great breakfast (special Alameda
at Sunnyside Café), I spent the next 4 hours digging this trench for
drainage pipe (left photo). PJ spent quite a bit of the time hanging
out and talking with me, which was quite enjoyable. On July 7th, Mike
glued the pipe in (right photo). I'll backfill the trench soon. |
 |
| July 5th. Today was a busy day for the
addition, with the roofers, plumbers and Mike/Tim onsite. With all of
these hardworking, hungry people Em decided to make them lunch. |
 |
| July 5th. Mike has started placing flashing over the cement
board which protects the foam which insulates the slab which is heated
by hot water which flows in PEX which stands for cross linked
polyethylene. When I took this photo I wondered how Mike was going to
protect the exposed foam. |
 |
| July 6th. And here's how Mike finished it. Yet another great
detail by MFB. |
 |
| July 5th. New flashing around the chimney. |
 |
| July 5th. Torch-down installation at the
flat part of the roof. You can't see the flame in the photo, but I
certainly felt it from where I took the photo. As of July 6th, the
roof is done except for the vents, which the roofers ordered but
haven't come in yet. |
 |
| July 6th. Manifold, in progress, for the
radiant floor heating system. |
 |
| July 7th. The upper sliding door is in and
all exterior trim at the windows and exterior corners is installed. |
 |
| July 7th. The soffits are also done. Note
the nice clean way the corner trim terminates under the redwood
fascia. |
 |
| July 7th. The 4" pvc pipe drains about 2/3
of the roof to the point where it daylights in the backyard. Any
water that collects under the addition will drain by gravity into the
green dry well, where a sump pump will push it out of the smaller pvc
pipe where it also daylights in the yard. |
 |
| July 7th. Here's the 4" pvc drain pipe at
the north side of the house, and its connection to the existing black
drain pipe. The drain for the water heater slab also ties into the 4"
pvc with two reducers (4" to 2" and 2" to 1 1/2"). |
 |
| July 7th. Mike is going on his 3-week
honeymoon in South Africa tomorrow, and the house is water-tight, so
we took down the temporary plastic wall. The stairs from the existing
house to the lower level are at the opening on the far left. The
three stairs from the existing house to the upper level of the
addition are behind the green chair on the left. |
 |
|
 |
| July 9th (before) and July 10th (after). One
of my pet peeves is when dirt, mulch, or rocks spill onto a driveway
or walkway. And it did on the north side of our house, so I dug
it out an put rock back. |
...to be continued...
[ Home ] [ Adventure ] [ Backpacking ] [ Food ] [ Events ] [ Projects ] [ PJ and E-Ling ]
|